Project Cost Estimator
Estimates total project cost by combining labor, materials, and overhead into a single budget. Includes a configurable contingency reserve and variance tracking against actuals as the project progresses.
Operations - Project Cost Estimator.xlsx
Excel (.xlsx) — No macros — Works in Excel, Google Sheets, LibreOffice
What This Spreadsheet Solves
- Projects exceeding budget because initial estimates omitted indirect costs
- No standard methodology for estimating project costs consistently
- Contingency reserves set arbitrarily rather than based on risk assessment
- Inability to compare estimated vs. actual costs during execution
- Stakeholders lacking confidence in cost projections
Who This Is For
- Project managers preparing budgets for approval
- Operations directors standardizing estimation processes
- Finance teams reviewing project cost proposals
- Program managers overseeing multi-project portfolios
Inputs
- #Labor hours by role
- $Hourly labor rate by role
- $Materials and equipment cost
- %Overhead rate
- %Contingency percentage
- #Project duration in weeks
Outputs
- Total labor cost
- Total materials cost
- Overhead allocation
- Contingency reserve amount
- Total project budget
- Cost per week
How Calculations Work
Labor cost is computed by multiplying hours by rate for each role. Materials are summed directly. Overhead is applied as a percentage of direct costs (labor plus materials). Contingency is calculated as a percentage of the total before contingency. The sum produces the total project budget. A phased breakdown distributes costs across the project timeline.
Example Use Case
Scenario: A software project requires 2 developers (400 hrs each at $85/hr), 1 designer (120 hrs at $75/hr), $3,000 in tools, 15% overhead, and 10% contingency over 16 weeks.
Result: Labor: $77,000. Materials: $3,000. Overhead: $12,000. Subtotal: $92,000. Contingency: $9,200. Total budget: $101,200. Cost per week: $6,325.
What You Get — 5 Sheets
Technical Details
Frequently Asked Questions
How do I set the contingency percentage?
5-10% for well-defined projects with experienced teams. 15-25% for projects with unclear scope or new technology. Base it on historical variance data if available.
Should I include internal staff at full salary cost?
Use a fully loaded rate (salary plus benefits plus overhead) for the most accurate estimate. The CONFIG sheet has a formula for converting salary to hourly rate.
How do I handle costs I cannot estimate precisely?
Use three-point estimation: enter optimistic, likely, and pessimistic values. The LOGIC sheet computes a weighted average.
Can I track actuals against the estimate?
Yes. The OUTPUT sheet has columns for actual costs that update the variance tracker as you enter real data.
What overhead rate should I use?
Typical ranges: 25-40% for professional services, 15-25% for tech companies, 40-60% for manufacturing. Use your company's actual overhead rate if known.
Download Project Cost Estimator
Ready to use immediately. Enter your data in the INPUT sheet, see results in OUTPUT.